Estimated Costs, Planned Costs and Actual Costs in a SAP?
For the purposes of this answer, regards
to a plant maintenance order.
Also, in this answer "costs"
equal job cost in resources, including internal labor, external labor, stock
and non-stock components, rentals, etc.
Estimated costs
would be manually calculated costs. You may see this figure manually entered on
the header of a PM order. You would use this figure for decision-making in
advance of planning.
Planned costs
are the total costs calculated after detailed planning of resources.
Actual costs
are the total costs incurred during/after execution of the work order,
including time confirmations (internal labor), sevice entry sheets (external
labor), material issued to the order from stock (reservations), non-stock
materials received (GR), and other costs such as rentals.
Cost flow in maintenance orders:
1. Estimated costs is an approximate
value, entered during creation of maintenance order. This value is for
information purposes only and will not be validated anywhere.
Estimated cost: You can enter this cost
manually in order Header.
In Header Data -> Costs while creation
of Order.
2. Planned costs is when external
procurement of spare(non-stock)/services are required, they are entered in the
maintenance order. The spares will have cost in material master.
Planned costs: After Confirmation of
operation, service etc cost will reflect.
Service cost is entered manually while
creation of maintenance order. These costs are calculated when the order is
brought to Release status, and appear as planned costs in the costs tab.
IW41 & IW42 are used for confirming
the task/operation with the time. This will accrued the cost of internal
operation to the order.
3. Subsequent purchasing activity PR to PO
conversion is done and when the material is inwarded, the actual cost as per
PO, flows to maintenance order and populated as Actual costs.
Same case happens when service entry sheet is created for external services.
4. Now the cost sits with the maintenance
order. This must be settled to a cost center, assigned to the equipment, for
which maintenance order is processed.
When actual settlement is done for the
order, the actual cost moves to the cost center and the order value becomes
zero. This activity is required from FI Controlling point of view, to accrued
the total expenses done on the equipment and adding them to the production cost
incurred, using that equipment.
Actual costs: After settlement actual cost
will appear.These cost can be viewed at Costs tab of Order.
KO88 is the only way you can do the actual
settlement.
TECO as name implies, is technical
completion of the order and associated notifications.
You will be able to do KO88 even after
TECO.
Post a Comment
Thanks for visiting our site : sapguidanceconsultant.blogspot.com
For Fast Response message us through "Contact Form".